Add Resource Results Dialog Box
Use this dialog box to add results to a resource or child resource.
Contents
Field | Description |
---|---|
Field Name | This field displays the field name of the result. |
Result | This field defaults to the entry in the Field Name column. You can modify the entry in this field. |
Units | Use this field to specify how the result is measured. For example, a unit of measurement might be dollars, or it might be tons. |
Rate Set | Use this field to specify the rate set to be used as a multiplier in the calculation. |
Currency | Selecting this option instructs Cobra to include this result in the totals of the Project view, the Project Audit, and the report totals. Typically, all results that are in the same currency as the currency defined in the Currency Symbol field of the General tab of the Project Properties dialog box are marked as a currency result. However, if majority of your reports do not include a result such as Fee, you have the option not to mark that result as a currency result. To report on Fee, you can create a calculated result that does have the currency flag. IPMR Format 3 reporting includes values found in the Project Audit log. To exclude Fee from the body of the IPMR Format 3, do not mark Fee as a currency result.
Note: Any result coded as a currency field must be used as a currency field for all resources within the resource file.
|
Result Code | The result code is used in reporting to identify specific results in a generic manner. |
- Related Topics:
- Display the Add Resource Results Dialog Box
Use this procedure to display the Add Resource Results dialog box.
Parent Topic: Calculations Tab of the Resource View
How to...